The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
a) function point
b) ratio
c) apportion
d) consensus
e) learning curves

Respuesta :

parisannthornton parisannthornton
  • 04-08-2021
The answer is e) learning curves
Answer Link

Otras preguntas

how many electrons are contained in a co3+ ion
which of the following is NOT an accurate description of world war ll? A it was the most widespread war in human history B it had the most advanced weapons in
what force is required to accelerate a body with the mass of 15 kilograms at a rate of 8m/s2?
how do you solve this? 5x-4y+6x if x=8
Which of the following means the same as concurrent powers
The table shows monthly profits and losses for Whitney's juice shop for a 6-month period. What is the net profit or loss for all six months? Two row table
How do you describe a neuron?
describe the three system related to the skeletal system
-1 1/6 - (-2 1/3) = Please explain how you got the answer! :)I need the answer quickly!!!
what force is required to accelerate a body with the mass of 15 kilograms at a rate of 8m/s2?